Noklak's 9-day blackout ends; district had no spare transformer
A failed 1.5 MVA transformer left Nagaland's Myanmar-border district dark from November 13 to 22, through exams. A 2.5 MVA replacement from Dimapur restored power; residents now want a standby unit.
By Ankur Borthakur (AI) · AI news writer · Published · 5 min read
Advertisement728×90 · Advertise with us · Gaming and esports brands welcome · [email protected]
Electricity returned to Noklak, the Nagaland district on the Myanmar border, on Sunday morning, November 22, ending a blackout that began on November 13 and ran through school examinations, Eastern Mirror reported.
The transformer at the Noklak Power Sub-Station failed, and the district had no standby unit. Power returned only after the Department of Power brought a larger replacement from Dimapur and installed it.
What failed, and how long each step took
Pieced together from Eastern Mirror, Hub News and The Morung Express reports:
- November 13: The existing transformer at the Noklak sub-station fails (Hub News). Eastern Mirror and Hub News put its capacity at 1.5 MVA; The Morung Express reported 1.6 MVA.
- November 13-17: Local repair attempts fail (Eastern Mirror).
- November 16: With exams under way, the Nokshou Students' Union and Baptist Church Nokyan 'B' open a tutoring centre in Noklak with generator-powered lighting so students can study after dark, Nagaland Tribune and Nagaland Post reported.
- November 18 (Wednesday): The faulty transformer is sent to Dimapur for inspection and repair, five days after it failed.
- November 20 (Friday): A replacement 2.5 MVA transformer reaches Noklak. Power staff still have to build a concrete foundation, install the unit and complete charging and commissioning checks, Hub News reported.
- November 22 (Sunday): Supply restored to Noklak town and surrounding villages.
A bigger transformer, on paper
The replacement is a real upgrade. At 2.5 MVA, it has about 67 per cent more capacity than the 1.5 MVA unit it replaces (about 56 per cent more if the 1.6 MVA figure is correct).
Capacity, however, was not what kept Noklak dark. Redundancy was. Eastern Mirror reported that the lack of a backup transformer in the district is what stretched the outage past a week, and residents have asked the department to keep a standby unit in Noklak.
What nine days without power meant in Noklak
Noklak was carved out of Tuensang as Nagaland's 12th district in December 2017. It covers 1,152 sq km across five circles (Noklak, Thonoknyu, Nokhu, Panso and Chingmei) and had 59,300 people at the 2011 Census, almost all of them Khiamniungan Naga.
The outage hit students hardest. Vikuonuo Sachü, founder of Miraculum Society Nagaland, runs an after-school centre in Noklak for about 200 children from Grades 1 to 8. She told Eastern Mirror that children were studying with "just the flicker of a candle" while adults held up torches. She also asked why the faulty transformer had been sent to Dimapur only on the sixth day.
Candles became hard to find, and residents went to the Assam Rifles camp to charge their phones, according to Eastern Mirror and Hub News.
The same week, the Reserve Bank of India's Kohima office held a meeting in Noklak village on November 19 as part of its adoption of the district for financial inclusion, according to a PIB release. Central Bank of India and HDFC Bank are expected to open branches in Panso and Thonoknyu blocks in the coming months.
Not just a Noklak problem
The same gap has hit bigger towns.
- Dimapur, July 2026: A 33/11 kV, 10 MVA transformer at the Supermarket sub-station failed. Hub News reported that the Department of Power had no spare 10 MVA unit in stock; the only spare at its Central Store was a 5 MVA unit. To restore supply, crews shifted a 22-tonne transformer from another sub-station with two Hydra cranes.
- Wokha, 2020: The district's 5 MVA transformer, installed in 2005, was "fully overloaded" after 15 years of rising demand, the executive engineer said in a DIPR Nagaland release. It took a second 5 MVA unit, commissioned on December 14, 2020, to bring Wokha to 10 MVA.
Even with its new transformer, Noklak's sub-station has a quarter of the 10 MVA that Wokha reached in 2020.
The department's stated targets for this year are about revenue and metering. Power Minister KG Kenye told the Assembly in September that the department collected Rs 324.81 crore in revenue in 2025-26 and expects Rs 400 crore in 2026-27, The Morung Express and Mokokchung Times reported. That rise depends on smart meters: 57,300 had been installed under the Centre's Revamped Distribution Sector Scheme (RDSS), against a target of 3,17,210 by February 2027.
For Noklak, an old story
On October 30, NEInsider reported that the Khiamniungan Students' Union had ended a shutdown of the PWD office only after the department promised priority to stalled roads, including the 31 km, Rs 164.80 crore Chendang Saddle-Noklak-Pangsha road (read the story).
What to watch
- The repaired unit: Neither the department nor any of the reports has said whether the 1.5 MVA transformer will return to Noklak as a standby once it is repaired in Dimapur. Residents have asked for exactly that.
- Board exams: Residents want a standby unit in place before students sit their board examinations, Eastern Mirror reported.
- RDSS deadline, February 2027: The 3.17 lakh smart-meter target falls due, the main RDSS yardstick the minister has cited.
NEInsider will update this story if the Department of Power states a plan for a standby transformer in Noklak.
Compiled by NEInsider with AI assistance from the sources credited below. How we use AI
Sources and credits. With inputs from Eastern Mirror (22 Nov) https://www.easternmirrornagaland.com/noklak-gets-power-back-after-nine-day-blackout ; Eastern Mirror (19 Nov) https://www.easternmirrornagaland.com/week-long-power-outage-forces-noklak-students-to-prepare-for-exams-in-the-dark ; Eastern Mirror (20 Nov) https://www.easternmirrornagaland.com/new-transformer-reaches-noklak-after-seven-nights-of-darkness ; Hub News (21 Nov) https://hubnetwork.in/seven-days-without-power-noklak-students-prepare-for-exams-by-candlelight/ ; The Morung Express (20 Nov) https://www.morungexpress.com/25-mva-transformer-arrives-in-noklak ; Nagaland Tribune (18 Nov) https://nagalandtribune.in/nokshou-students-union-baptist-church-launch-tutoring-initiative-in-noklak/ ; Nagaland Post (20 Nov) https://nagalandpost.com/nokshou-union-aids-students-amid-power-cuts/ ; PIB/RBI Kohima (19 Nov) https://www.pib.gov.in/PressReleasePage.aspx?PRID=2338681 ; background: Hub News (12 Jul) https://hubnetwork.in/dimapur-blackout-exposes-nagalands-fragile-power-infrastructure/ ; DIPR Nagaland (14 Dec 2020) https://ipr.nagaland.gov.in/wokha-installs-additional-5-mva-adequate-power-supply ; The Morung Express (1 Sep) https://www.morungexpress.com/power-department-collected-32481-cr-revenue-during-2025-26 ; Mokokchung Times (2 Sep) https://mokokchungtimes.com/power-dept-targets-rs-400-crore-revenue-in-fy27-3-17-lakh-smart-meters-by-feb-2027/ ; Census 2011 via Wikipedia https://en.wikipedia.org/wiki/Noklak_district
Share this story
Forward it to your family WhatsApp group. News from home travels fastest there.
Advertisement300×250 · Advertise with us · Gaming and esports brands welcome · [email protected]