Sonitpur solar plant starts supplying 45 MW, seven months behind target

SJVN's subsidiary declared 45 MW of its 50 MW Sitalmari plant commercial on November 21, against a CM target of April. The documents, the timeline from 2023, and what it means for Assam's 3,500 MW solar goal.

By · AI news writer · Published · 5 min read

Dhekiajuli town in Sonitpur district, Assam; the solar plant is in the Dhekiajuli revenue sector
Dhekiajuli town in Sonitpur district, Assam; the solar plant is in the Dhekiajuli revenue sector. Photo: John Akash Kangaria / Wikimedia Commons, CC BY-SA 3.0

SJVN Green Energy Limited (SGEL) has started selling power from 45 MW of its 50 MW solar plant in Sonitpur district, the central power company's second solar plant in Assam, about seven months after Chief Minister Himanta Biswa Sarma said it would be finished.

The SJVN subsidiary declared commercial operation of 45 MW (AC) on November 21, 2026, according to its regulatory filing as reported by pv magazine India, Saur Energy and Solarbytes. "The trial run certificate for the project was issued by APDCL vide letter dated 21.11.2026, and the project achieved commercial operation on 21.11.2026," SGEL said, pv magazine India reported. The remaining 5 MW has not yet been declared commercially operational.

What the documents show

The filing and earlier official releases give a fairly complete paper trail for the plant:

  • Location: Sitalmari village in the Barsola block, under the Dhekiajuli revenue sector of Sonitpur district, according to a March 2024 Press Information Bureau (PIB) release and Saur Energy.
  • Cost: an estimated Rs 291 crore, or about Rs 5.8 crore per megawatt.
  • Buyer: Assam Power Distribution Company Limited (APDCL), under a power purchase agreement signed on February 7, 2024, for all 50 MW.
  • Price: Rs 3.92 per unit, fixed through competitive bidding, the same tariff as SJVN's 70 MW Dhubri plant.
  • Output: about 101 million units a year once the full 50 MW runs, and roughly 2,319 million units over 25 years, PIB said.
  • Builder: Solarworld Energy Solutions is the engineering, procurement and construction contractor, under three letters of award dated March 20, 2024, pv magazine India reported.

On NEInsider's arithmetic, 101 million units a year at Rs 3.92 works out to about Rs 40 crore of power purchases a year for APDCL from this one plant.

Timeline: from groundbreaking to grid

  • August 2023: SGEL wins three APDCL solar tenders in Assam of 50 MW, 70 MW and 200 MW (320 MW in total) (with the letter of award signed that month), Energetica India reported. The 200 MW project was bid at Rs 3.90 per unit.
  • February 7, 2024: PPA for the Sonitpur 50 MW signed with APDCL.
  • March 2024: Chief Minister Sarma performs the Bhumi Pujan for the plant, with minister Ashok Singhal, Tezpur MP Pallab Lochan Das and Barchalla MLA Ganesh Kumar Limbu present, according to PIB.
  • January 15, 2026: Inaugurating the 70 MW Dhubri plant at Khudigaon near Bilasipara, Sarma said "Another 50 MW project being implemented by SJVN at Borsolla in Sonitpur district will be completed by April, and we will reach 730 MW then," ET EnergyWorld reported.
  • February 2026: SJVN declares commercial operation of the Dhubri plant, built for Rs 367.44 crore and described by the company as Assam's first large-scale solar project, Energetica India reported.
  • November 21, 2026: 45 MW of the Sonitpur plant enters commercial operation.

From groundbreaking to first commercial power, the Sonitpur plant took about 32 months.

What this means for Assam

The 101 million units the plant can produce in a full year are small against Assam's needs. As NEInsider reported on November 10 (be96f0), the Central Electricity Authority projects the state's annual requirement at 14,978 million units in 2026-27, rising to 18,162 million units by 2029-30, with peak demand climbing from 2,915 MW to 3,403 MW. On those figures, the Sonitpur plant at full output would cover well under 1 per cent of this year's need.

Its value lies in where the power comes from. Assam buys a significant share of its electricity from outside the state, and the plant's 25-year price of Rs 3.92 is fixed. In the state budget in July, Finance Minister Jayanta Mallabaruah said the government wants to take the state's own generation capacity from about 450 MW to 8,457 MW with Rs 77,353 crore of planned investment, ET EnergyWorld reported. Solar is part of that plan: in January the Chief Minister put Assam's solar capacity at 680 MW and set a target of 3,500 MW by 2030.

For Sonitpur, in March 2024, PIB said it would bring about Rs 291 crore of investment to the area. Neither SGEL's filing nor the reports on it say how many local jobs the plant has created.

What happens next

  • The last 5 MW: SGEL has not given a date for declaring the rest of the 50 MW commercial. NEInsider will update this story when it does.
  • The 200 MW project: NEInsider could not find a public commissioning date for SGEL's largest Assam award, the 200 MW project bid at Rs 3.90 per unit in 2023.
  • The state's count: No updated official figure for Assam's total solar capacity has been published since the Chief Minister's January figure of 680 MW. With about 2,800 MW still to add before 2030, the pace of projects like Sonitpur and Dhubri will decide whether the 3,500 MW target is met.

Compiled by NEInsider with AI assistance from the sources credited below. How we use AI

Sources and credits. With inputs from pv magazine India (23 Nov 2026) https://www.pv-magazine-india.com/2026/11/23/sjvn-commissions-45-mw-solar-in-assam/ ; Saur Energy (23 Nov 2026) https://www.saurenergy.com/solar-energy-news/svn-commissions-partially-commisisons-50-mw-sonitpur-solar-project-in-assam-12832902 ; Solarbytes (23 Nov 2026) https://solarbytes.info/india-bytes/sjvn-puts-45-mw-of-its-sonitpur-solar-project-in-assam-into-operation-12833974 ; PIB (March 2024) https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=2013269 ; ET EnergyWorld (15 Jan 2026) https://energy.economictimes.indiatimes.com/news/renewable/assams-ambitious-plan-3500-mw-solar-power-by-2030-announces-cm-himanta-biswa-sarma/126545077 ; Energetica India (16 Jan 2026) https://www.energetica-india.net/news/assam-cm-inaugurates-sjvn-70-mw-solar-project-at-bilasipara ; Energetica India (7 Feb 2026) https://www.energetica-india.net/news/sjvn-achieves-cod-of-70-mw-dhubri-solar-power-project-in-assam ; ET EnergyWorld (17 Jul 2026) https://energy.economictimes.indiatimes.com/news/power/assam-plans-77353-crore-investment-to-generate-8457-mw-power-aims-to-become-energy-surplus-state/132454020