Meghalaya · Environment · East Khasi Hills
Marten leachate leak: KSU-SMB inspection finds seepage toward Umiam
A joint inspection on November 21 found contaminated water seeping from Shillong's only landfill and parts of its treatment system not working, the KSU says. A year ago the same runoff was traced to Umiam Lake.
By Ankur Borthakur (AI) · AI news writer · Published · 5 min read

Advertisement728×90 · Advertise with us · Gaming and esports brands welcome · [email protected]
Contaminated water is seeping out of Shillong's Marten dumpsite at Mawiong, and parts of the system meant to contain and treat it are not working properly, the Khasi Students' Union (KSU) Mawlai Circle said on Monday, November 23. The union reported this after a joint inspection with Shillong Municipal Board (SMB) officials on Saturday, November 21. It says the leak puts the Umïam River and Umïam Lake at risk.
Syllad, Hub News, Shillong Today and Ukhrul Times carried the account. The SMB and Urban Affairs Department had not responded publicly by early Tuesday.
What the inspection found
After repeated complaints from residents, the KSU wrote to the Commissioner and Secretary of the Urban Affairs Department on November 2, then inspected the site on November 21 with SMB Executive Engineer F. B. Chyne and other board staff.
The union says it found:
- Leachate leaking: "a large amount of dirty water leaking from the dumpsite", in the KSU statement quoted by Hub News.
- Equipment problems: some parts of the leachate treatment equipment and the protective barriers were "not functioning properly", according to the statement.
- Risk downstream: catchment areas and water sources nearby, and above all Umïam Lake, which the union said supports fisheries, drinking water supply, power generation and tourism.
The KSU wants an immediate assessment of the leak, a properly maintained treatment plant, stronger barriers and regular water-quality monitoring along the Umïam River and lake. "The authorities should not wait until the environmental damage becomes irreparable, before taking steps," the union said, as quoted by Syllad and Hub News.
These are the union's findings; the SMB has published no record of the inspection and no water tests have been released.
Marten in figures
Official figures given to the Meghalaya Assembly show why the site is under strain:
- Age and size: Marten has been in use since 1938 and covers about 18 acres. It is Shillong's only landfill, on land from the Riatkhwan Reserved Forest leased from the Forest Department, with an extension secured until 2026, Deputy Chief Minister Sniawbhalang Dhar told the House in March 2025 (India Today NE).
- Design versus reality: the landfill phases were planned to last three and seven years on the assumption that only 10% of the city's waste would end up there. In March 2025 about 23% was still reaching the landfill, with Shillong generating an estimated 196 tonnes a day.
- Legacy waste: in the March 2026 Budget Session, Dhar said 2,24,143 tonnes of the site's 3,45,996 tonnes of old waste had been bio-mined, leaving 1,21,193 tonnes, with June 2026 as the completion target (India Today NE). The Rs 24.40 crore contract had used Rs 12.75 crore by then. No Environmental Impact Assessment was done, he said, because bio-mining did not count as a new project, and no penalty had been imposed on the contractor for delays.
A year ago, the same warning
Almost exactly a year ago, on November 24, 2025, The Shillong Times reported that garbage at Marten stood nearly twice as high as the retaining walls, and that pipes under the wall were releasing dark water into roadside drains that run to Umïam Lake. An SMB official told the paper then that all wastewater "is supposed to be taken first" to the leachate treatment plant, "filtered, and released only after proper treatment". The same report said the share of waste processed rather than dumped rose from 19% in early 2023 to 87% by July 2025.
The KSU's complaint now is that the treatment system itself is not working as it should.
How we got here
- April 2022: the Meghalaya High Court said Marten should be closed if it had reached saturation, once an alternative site was found for immediate use, Highland Post reported. A 112-acre site at Nonghali was later proposed, and an environmental study was under way in March 2025.
- November 1, 2026: the Hynniewtrep National Youth Front and residents of Mawlai Nongkwar found a cracked retaining wall and black water flowing toward Umïam, and asked for dumping to stop (our report).
- November 2026, at the lake: while Marten drains toward it, Umïam is also being sold as a tourism hub. IHCL signed a Taj hotel near the lake (our report).
What it means locally
For families in Mawlai and Mawiong, it means stench, runoff on the old Guwahati-Shillong road and worry over water sources. Downstream, Umïam is a reservoir that feeds hydropower, fish farms and a growing tourism business. Two youth bodies have now inspected Marten in three weeks and reported the same problem: dirty water heading for the lake.
What happens next
- Response to the KSU: the union wants "genuine actions showing work on the ground". Watch for an SMB or Urban Affairs statement, repairs, or water-quality test results.
- Bio-mining: the June 2026 completion target has passed. NEInsider found no public statement on whether the remaining 1,21,193 tonnes have been cleared.
- Forest lease: the extension cited in March 2025 runs only until 2026, so the government needs to renew it or move dumping to Nonghali or elsewhere soon.
Compiled by NEInsider with AI assistance from the sources credited below. How we use AI
Sources and credits. With inputs from Syllad (23 Nov 2026) https://www.syllad.com/ksu-flags-leachate-leakage-at-marten-warns-of-threat-to-umiam/ ; Hub News (23 Nov 2026) https://hubnetwork.in/ksu-flags-marten-dumpsite-leachate-leak-warns-of-threat-to-umiam/ ; Shillong Today (23 Nov 2026) https://shillongtoday.com/ksu-raises-alarm-over-leachate-seepage-at-marten-dumpsite-seeks-immediate-inspection/ ; Ukhrul Times (23 Nov 2026) https://ukhrultimes.com/meghalaya-ksu-mawlai-leachate-seepage-marten-dumpsite-immediate-inspection/ ; India Today NE (1 Mar 2026) https://www.indiatodayne.in/meghalaya/story/meghalayas-marten-landfill-clean-up-nears-finish-line-after-years-of-slog-1353158-2026-03-01 ; India Today NE (12 Mar 2025) https://www.indiatodayne.in/meghalaya/story/shillongs-marten-dumping-site-struggles-to-handle-rising-waste-future-uncertain-1183073-2025-03-12 ; The Shillong Times (24 Nov 2025) https://theshillongtimes.com/2025/11/24/umiam-suffers-as-marten-waste-dump-exceeds-carrying-capacity/ ; The Shillong Times (2 Nov 2026) https://theshillongtimes.com/2026/11/02/marten-landfill-turns-toxic-damaged-wall-black-water-stench-raise-disaster-fears/ ; Highland Post (8 Apr 2022) https://highlandpost.com/marten-must-be-shut-once-new-landfill-site-is-found-hc/
Share this story
Forward it to your family WhatsApp group. News from home travels fastest there.
Advertisement300×250 · Advertise with us · Gaming and esports brands welcome · [email protected]