Umroi runway stretch to 2,400 m on track for Dec 2027, says Meghalaya

Shillong Airport's Rs 488.67 crore expansion should finish by December 2027, a month or two beyond the timelines implied in April and August. The High Court takes it up again on December 14.

By · AI news writer · Published · 5 min read

Shillong Airport terminal building, Narapati, Murli, Shillong, Meghalaya
Shillong Airport terminal building, Narapati, Murli, Shillong, Meghalaya. Photo: आशीष_भटनागर / Wikimedia Commons, CC BY-SA 3.0

Meghalaya's Transport and Civil Aviation Department says the expansion of Shillong Airport at Umroi is on schedule to finish by December 2027. Department Secretary Sanjay Goyal said on November 23 that construction is "in full swing", is following the approved master plan, and that there is no reason to expect a delay, The Shillong Times and Northeast Today reported.

Umroi can now take only ATR 72 turboprops. The longer runway is meant to let narrow-body jets from metro cities land in Ri Bhoi.

The project in numbers

Figures from the environmental clearance, the state's filings in the Meghalaya High Court and reports since April:

  • Runway: 1,829 m extended to about 2,400 m, an addition of 571 m towards the Runway 04 end
  • Terminal: domestic terminal to grow from 5,000 sq m to 10,550 sq m, more than double, with a bigger apron
  • Cost: Rs 488.67 crore estimated, including Rs 1.24 crore for the environmental management plan (environmental clearance of March 28, 2026, as reported by The Shillong Times in September)
  • Land: 168.41 hectares of non-forest land in all; the state had to acquire an extra 22 acres (16 for the Runway End Safety Area and 6 for an isolation bay). It told the High Court it has acquired 17.68 acres on the Runway 04 side, more than the 16 needed for the safety area, Hub News reported on November 4
  • Contractor: KCC Buildcon Pvt Ltd, work order dated April 1, 2026, with an 18-month construction period that includes three monsoon months, according to a state submission cited by EastMojo

How December 2027 compares with earlier promises

  • April 1, 2026: work order issued. On paper, an 18-month clock would have ended around October 2027.
  • June-July 2026: the High Court pulled up the Directorate General of Civil Aviation (DGCA) over the pending execution-stage safety clearance, The Shillong Times reported.
  • August 4, 2026: DGCA granted execution-level approval for the Runway 04 side, subject to 10 conditions. The state undertook to clear flight-path obstacles by September 30 (Highland Post).
  • August 7, 2026: the Ri Bhoi Deputy Commissioner barred new construction or alterations on land marked for the project in Umden Mission village, India Today NE reported.
  • August 13, 2026: Chief Minister Conrad K Sangma announced that runway work had started and gave it "a maximum period of 15 months", which points to roughly November 2027.
  • November 3-4, 2026: the Airports Authority of India (AAI) told the High Court that excavators and earth-moving machinery were on site and that staff quarters in front of the old terminal were being demolished. NEInsider reported this in High Court notes commencement of Shillong Airport expansion.
  • November 23, 2026: December 2027 named as the completion date for the whole expansion.

So the official finish line is now one to two months beyond the timelines implied in April and August.

What it means for Ri Bhoi and air travellers

For people in Umroi and nearby villages, the biggest practical issue is access. The state told the High Court that the land deal includes a road along the new airport boundary wall so neighbouring villages keep their routes. The alignment was surveyed with AAI, the Public Works Department and the Land Records department on October 8, and PWD is still preparing cost estimates. The road cannot be built until AAI fixes the final line of the boundary wall.

For travellers, the gap is large. In July The Shillong Times reported that Umroi had scheduled flights only to Kolkata (daily), New Delhi (twice a week), Imphal, Aizawl and Pasighat. Earlier UDAN links to Dimapur, Silchar, Dibrugarh and Agartala had lapsed once viability-gap funding ran out. The same report said the state's tenders for direct flights to Mumbai, Hyderabad and Bengaluru stalled when airlines asked for more subsidy than the government would pay. Until the longer runway opens, most Shillong flyers will still make the long road trip to Guwahati's airport.

Deputy Chief Minister Sniawbhalang Dhar has said the expansion could create "minimum 20,000" direct and indirect jobs, The Meghalayan Express reported on October 29.

Part of a wider North East airfield push

Meghalaya has signed an MoU with AAI to revive Baljek Airport near Tura. Arunachal Pradesh is reviewing an airfield at Anini and consulting villages on a greenfield airport at Oyan. Umroi is the furthest along, with a contractor on site.

What happens next

  • December 14, 2026: the High Court's next hearing in PIL No. 4/2021. AAI and the state have been told to file fresh status reports.
  • Pending: whether all flight-path obstacles were removed by the September 30 undertaking, and PWD's estimate for the village access road. Neither has been made public.
  • December 2027: the department's completion target for the runway, terminal and apron.

NEInsider will update this story after the December 14 hearing.

Compiled by NEInsider with AI assistance from the sources credited below. How we use AI

Sources and credits. With inputs from The Shillong Times (24 Nov 2026) https://theshillongtimes.com/2026/11/24/shillong-airport-expansion-on-track-for-dec-2027-finish/ ; Northeast Today (23 Nov 2026) https://northeasttoday.in/northeast/meghalayas-shillong-airport-set-for-major-upgrade-expansion-targeted-by-december-2027/ ; Hub News (4 Nov 2026) https://hubnetwork.in/shillong-airport-expansion-takes-off-meghalaya-hc-told-runway-work-underway-road-for-villages-in-pipeline/ ; The Shillong Times (15 Sep 2026) https://theshillongtimes.com/2026/09/15/shillong-airport-eyes-bigger-terminal-runway-as-expansion-work-progresses/ ; EastMojo (14 Aug 2026) https://eastmojo.com/meghalaya/2026/08/14/shillong-airport-runway-expansion-begins-larger-aircraft-expected-by-2027/ ; India Today NE (7 Aug 2026) https://www.indiatodayne.in/meghalaya/story/ri-bhoi-administration-bans-new-construction-in-umden-for-shillong-airport-expansion-1434947-2026-08-07 ; Highland Post (6 Aug 2026) https://highlandpost.com/shillong-airport-expansion-dgca-grants-execution-approval/ ; The Shillong Times (3 Jul 2026) https://theshillongtimes.com/2026/07/03/tardy-umroi-airport-expansion-work-hits-passengers-hard/ ; The Meghalayan Express (29 Oct 2026) https://themeghalayanexpress.com/shillong-airport-expansion-can-create-20000-jobs-dy-cm/