Assam · Politics · Cachar
Silchar flyover rethink: Rs 700-cr two-flyover plan draws legal notice
A 3.5-km elevated corridor whose foundation stone the PM laid in March may become two short flyovers and a four-lane road. A Silchar lawyer has given officials 15 days to explain the change. Here are the numbers, the dates and what comes next.
By Ankur Borthakur (AI) · AI news writer · Published · 5 min read

Advertisement728×90 · Advertise with us · Gaming and esports brands welcome · [email protected]
Silchar's long-promised flyover is being redrawn before full construction has even begun. At a meeting in the Cachar Deputy Commissioner's office on Friday, November 20, Housing and Urban Affairs Minister Kaushik Rai put forward a new plan: in place of one continuous 3.5-km elevated corridor between Capital Point and Rangirkhari, the city would get two short flyovers and a widened four-lane road. The estimated cost is now about Rs 700 crore.
Within a day, a Silchar lawyer had written to the Prime Minister's Office and sent a pre-litigation notice to five senior officials, warning he may go to the Gauhati High Court.
What changes on the ground
According to the details Rai shared after the meeting, reported by The Assam Tribune and Barak Bulletin, the revised package has three parts:
- Road widening: about 2.5 km from Capital Point to Gopinath Cinema Hall becomes four-lane, with a divider, drains and footpaths.
- Flyover one: about 542 metres, from Krishnacharan Pathshala to Gopinath Cinema Hall.
- Flyover two: about 500 metres, from Sadarghat to the Radio Station area.
Other reports describe the flyover ends slightly differently, and the PWD has not yet published the exact alignment. Rai said the detailed design would be shared once the government clears it.
He told The Assam Tribune that everyone at the meeting, including those who had earlier objected to the flyover, agreed to the new plan. The Times of India reported that the original corridor had faced opposition from some traders who were worried about its effect on shops along the route. Rai also admitted, according to Pratidin Time, that land acquisition costs would now be "much higher" than before.
The numbers behind the original project
The figures reported so far for the original corridor do not all match:
- Cabinet approval: September 9, 2025. The Times of India put the cost at Rs 583 crore. Northeast Live gave a range of Rs 564.50 crore to Rs 583 crore, and Pratidin Time quoted Rs 565 crore.
- Land acquisition: lawyer Dharmananda Deb told Pratidin Time that Rs 100 crore for land was approved by the cabinet on October 6, 2025. The Assam Tribune reported that his memorandum asks about a Rs 147-crore land allocation.
- Tender: the Times of India reported that Deb is also questioning a Rs 399.30-crore tender issued in September 2025, before the cabinet approved the project.
- Foundation stone: Prime Minister Narendra Modi laid it on March 14, 2026, during his Cachar visit.
- Technical work: soil investigations began in July. Between November 16 and 18, engineers ran a three-day load test on a 30-metre-deep pile near Silchar Civil Hospital, applying about 1,014 tonnes against a design load of about 550 tonnes. No structural distress was found, the Times of India reported.
As late as November 18, Northeast Live reported a December construction start, while noting that other alignments were being studied because of land problems.
The legal challenge
Deb, described by Hub News as a former Foreigners Tribunal judge, has practised in Silchar for about 24 years. He sent his representation to the PMO, with copies to Union Road Transport Minister Nitin Gadkari and Barak Valley Development Minister Krishnendu Paul. According to the Times of India, his pre-litigation notice asks for 21 documents and explanations. These include the original detailed project report, the soil and pile-test records, the technical assessments behind the change and the minutes of the November 20 meeting.
His main point, reported by Hub News and The Assam Tribune, is that a review meeting cannot replace formal technical and administrative approval for changing a cabinet-sanctioned project. "Silchar does not seek assurances. Silchar seeks transparency, accountability and the infrastructure development promised to its people," he wrote in the memorandum, as quoted by The Assam Tribune and Hub News.
The opposition has also pushed back. Pradesh Congress spokesperson Sanjeev Rai told Pratidin Time that two flyovers of about 500 metres each were a "lollipop" for the people of Silchar. He said the BJP had promised a flyover since its 2016 manifesto.
What it means for Silchar commuters
The Capital Point-Rangirkhari stretch along NH-306 is one of Silchar's worst bottlenecks. It is also the route to Silchar Medical College and Hospital, NIT Silchar and Assam University. Northeast Live reported that a 10-minute trip on this road can take one to two hours at peak times.
Two short flyovers may spare shopfronts, but the plan needs more land on a busy commercial strip and leaves most of the 3.5 km at street level. A new design and land process could also delay a start that was due next month.
What happens next
- The PWD Commissioner and Chief Engineer are to send the revised Rs 700-crore proposal to Chief Minister Himanta Biswa Sarma for approval. Further administrative clearances are needed before work can start.
- Deb's notice, sent on November 21, gives the officials 15 days to reply, which means about December 6. After that he says he will consider a PIL under Article 226 in the Gauhati High Court.
- No one has yet said what happens to land already acquired, the existing tender or the December start.
NEInsider will update this story when the state government clears or changes the proposal, or if the matter reaches court.
Compiled by NEInsider with AI assistance from the sources credited below. How we use AI
Sources and credits. With inputs from Hub News (23 Nov) https://hubnetwork.in/assam-silchar-flyover-redesign-sparks-questions-project-cost-reportedly-rises-to-rs-700-crore-lawyer-moves-pmo/ ; The Assam Tribune (21 Nov) https://assamtribune.com/assam/silchar-elevated-corridor-gets-rs-700-crore-rethink-with-two-flyovers-new-road-1623100 ; The Assam Tribune (22 Nov) https://assamtribune.com/assam/silchar-flyover-lawyer-moves-pmo-over-proposed-cut-rs-147-cr-land-acquisition-1623137 ; Barak Bulletin (20 Nov) https://barakbulletin.com/59617-2/ ; The Times of India (21 Nov) https://timesofindia.indiatimes.com/city/guwahati/assam-revises-silchar-corridor-plan-after-trader-opposition-proposes-rs-700cr-alternative/articleshow/136036811.cms ; The Times of India (21 Nov, notice) https://timesofindia.indiatimes.com/city/guwahati/pre-litigation-notice-to-assam-govt-over-silchar-corridor-plan-revision/articleshow/136059211.cms ; Pratidin Time (21 Nov) https://www.pratidintime.com/latest-assam-news-breaking-news-assam/assam-silchar-flyover-axed-for-4-lane-road-lawyer-writes-to-pmo-eyes-pil-12830002 ; The Times of India (19 Nov, load test) https://timesofindia.indiatimes.com/city/guwahati/silchar-flyover-clears-load-test-panel-reviews-progress/articleshow/136000421.cms ; Northeast Live (18 Nov) https://northeastlivetv.com/around-ne/assam/assam-around-ne/silchar-flyover-construction-expected-to-begin-in-december-major-infrastructure-boost-for-barak-valley/ ; India Today NE (20 Nov) https://www.indiatodayne.in/assam/story/assam-evaluates-alternative-plans-for-silchar-elevated-corridor-to-ease-traffic-congestion-1477915-2026-11-20