Majuli's Kamalabari ferry moves to Bamungaon as Brahmaputra drops

Boats to Neamatighat now dock at a new landing near Bamungaon, just before Raas. The Rs 1,108-crore Jorhat-Majuli bridge that would end the ferry dependence is about a third built and due in December 2027.

By · AI news writer · Published · 5 min read

Kamalabari ferry ghat on Majuli island, Assam (file photo)
Kamalabari ferry ghat on Majuli island, Assam (file photo). Photo: Indranil Gayan / Wikimedia Commons, CC BY-SA 4.0

Ferries between Majuli and Jorhat will leave from a new landing point near Bamungaon from Monday, November 16, because the Brahmaputra has fallen too low for boats to dock at the old Kamalabari ghat. India Today NE, Pratidin Time and Northeast News all reported the move on November 15 and 16. They said the river had dropped unusually sharply and boats could no longer dock and sail safely at the old site.

The Kamalabari crossing is Majuli's main link with Neamatighat (Nimati Ghat) in Jorhat district. Pratidin Time said the ghat has been moved ahead of its earlier position, towards Bamungaon. All three outlets said the crossing should now be shorter. The shops and stalls that served passengers at the old ghat have moved to the new landing point too.

The reports did not give the new crossing time; passengers should check with Inland Water Transport (IWT) counters before travelling.

What it means for Majuli

Majuli became a district in September 2016, carved out of Jorhat. The 2011 Census counted about 1.67 lakh people on the island. There is still no road bridge to Jorhat, which has the nearest railway station, airport, medical college and main markets. Students, patients, traders and government staff cross by boat, and the ghat at Kamalabari is where most of that traffic lands.

A changing landing point is not new. In November 2024 the Majuli Deputy Commissioner told The Assam Tribune that IWT had readied a third ghat at Dakhinpat for the Neamatighat route. That was on top of the Kamalabari and Afalamukh ghats, and it was opened in time for the Raas festival. As the river's channels shift each dry season, ghats follow the deep water.

The timing matters this year. Raas, Majuli's biggest festival, follows the Kartik full moon, and Raas Purnima falls on November 24. Thousands of visitors cross to the satras for the all-night Krishna plays. In 2024 the district raised boat frequency on all routes for the festival, The Assam Tribune reported. Moving the busiest landing point barely a week before this year's festival puts the pressure on IWT to get signage, queues and parking at Bamungaon working quickly.

Why ferry safety still worries islanders

Ferry trouble near Neamatighat has turned deadly before. On September 8, 2021, the private boat Ma Kamala collided with the government ferry Tripkai near Neamatighat and sank. The Assam State Disaster Management Authority said about 90 people were on the Ma Kamala, The Hindu reported. Three people died: college teacher Parimita Das, Indreswar Bora and doctor Bikramjit Barua, whose body was found about 30 km downstream a week later, according to NDTV. Three IWT officials were suspended, India Today reported. The Hindu noted then that the single-engine boat, like most country ferries on the river, was running without following safety guidelines.

The bridge that would end the wait

The permanent fix is the Jorhat-Majuli bridge, and it is still more than a year away. In a written reply in the Assam Assembly this year, Chief Minister Himanta Biswa Sarma said the 6.81-km bridge costs Rs 1,108.20 crore, was 34.35% complete and is due by December 10, 2027, The Times of India reported. Finance Minister Jayanta Mallabaruah's July 10 budget speech put the project at Rs 1,400 crore including approach roads, with completion in December 2027 (News Live).

The project has slipped before. The Chief Minister performed the bhoomi pujan in 2021, but work stopped in late 2024 after disputes between the earlier contractors, UP State Bridge Corporation Ltd and Badri Rai Company, and technical trouble, according to The Times of India. Work restarted in January 2026 under a fresh contract with SPS Construction India, with a two-year target (The Assam Tribune). At that point the bridge was described as an 8-km, Rs 925-crore project on 72 pillars. The Assembly figure is about Rs 183 crore (roughly 20%) higher, by NEInsider's arithmetic.

On a site visit, Majuli MLA Bhuban Gam put progress at 35% and said the bridge would be ready "by 2028", The Times of India reported. Work had started on every pillar except one in the middle of the river.

Compare that with the other two Brahmaputra bridges in the same Assembly reply: Jogighopa (4.385 km, Rs 746.76 crore) was 82% done with a March 31, 2027 deadline, and Palasbari-Sualkuchi (3.6 km, Rs 3,197.20 crore) was 50% done with a June 6, 2028 target. The Majuli bridge is the longest of the three and the furthest behind.

What happens next

  • From November 16: Kamalabari-Neamatighat boats use the new landing near Bamungaon.
  • Around November 24: Raas Purnima, when festival traffic peaks.
  • Through the dry season: ghats may move again as the river keeps falling.
  • December 10, 2027: official completion target for the Jorhat-Majuli bridge.

Related: Majuli's mask-makers, Mising council polls in Majuli, Assam's flood plain zoning bill.

Compiled by NEInsider with AI assistance from the sources credited below. How we use AI

Sources and credits. With inputs from India Today NE https://www.indiatodayne.in/assam/story/assam-kamalabari-ferry-services-in-majuli-to-shift-to-new-ghat-near-bamungaon-from-november-16-1475767-2026-11-15 ; Pratidin Time https://www.pratidintime.com/latest-assam-news-breaking-news-assam/majuli/majuli-kamalabari-ferry-ghat-new-landing-point-12811824 ; Northeast News https://nenews.in/assam/assam-majulis-kamalabari-ferry-services-to-operate-from-new-ghat-near-bamungaon/71046/ ; The Times of India (Assembly reply) https://timesofindia.indiatimes.com/city/guwahati/assam-to-get-3-bridges-by-2028-4th-awaits-centres-nod-cm-to-house/articleshow/132668484.cms ; The Times of India (MLA visit) https://timesofindia.indiatimes.com/city/guwahati/35-work-done-majuli-jorhat-bridge-to-be-ready-by-2028-mla/articleshow/131683590.cms ; The Assam Tribune (Jan 2026) https://assamtribune.com/assam/jorhatmajuli-bridge-work-resumes-completion-targeted-within-two-years-1605444 ; News Live https://newslivetv.com/majuli-jorhat-bridge-to-be-completed-by-dec-2027/ ; The Assam Tribune (Nov 2024) https://assamtribune.com/assam/majuli-to-celebrate-raas-from-nov-15-17-new-ghat-ready-for-boat-service-to-and-from-jorhat-1557906 ; The Hindu (2021) https://www.thehindu.com/news/national/other-states/body-of-missing-person-from-assam-ferry-mishap-recovered/article36400737.ece ; NDTV (2021) https://www.ndtv.com/india-news/assam-boat-tragedy-death-count-rises-to-3-as-body-of-last-missing-person-found-2541113 ; India Today (2021) https://www.indiatoday.in/india/story/assam-boat-tragedy-jorhat-updates-missing-death-toll-indian-army-air-force-rescue-operations-1850818-2021-09-09

Share this story

Forward it to your family WhatsApp group. News from home travels fastest there.