Sikkim's first railway now due June 2028, six months past last target
NFR told Sikkim's Chief Minister the 44.96-km Sivok-Rangpo line will be finished by June 2028. All year the target had been December 2027, and the state is being asked to help clear pending issues.
By Ankur Borthakur (AI) · AI news writer · Published · 4 min read

Advertisement728×90 · Advertise with us · Gaming and esports brands welcome · [email protected]
Sikkim's first railway line now has a new finish date: June 2028. That is six months later than the December 2027 target the Northeast Frontier Railway (NFR) repeated through most of this year.
The new date came out of meetings in Gangtok on Tuesday (November 17). NFR (Construction) General Manager Ashish Bansal briefed Chief Minister Prem Singh Tamang, Lok Sabha MP Indra Hang Subba and Chief Secretary Ravindra Telang on the 44.96-km Sivok-Rangpo New Railway Line, The Morung Express and IANS reported on Wednesday. NFR's Chief Public Relations Officer Kapinjal Kishore Sharma said the project "is targeted to be completed by June 2028", according to the IANS report carried by The Hawk. No reason was given for the later date.
What was discussed in Gangtok
Bansal took the Chief Minister through construction progress and steps to speed it up, and updated him on surveys for two possible extensions, Rangpo-Saramsa (Saramsa is near Ranipool, below Gangtok) and Melli-Dentam.
With the Chief Secretary, both reports said, the talks covered issues that need the state government to step in and a proposed NFR-state coordination framework. Neither report named the issues.
A target that keeps moving
The June 2028 date is the latest in a series of revised deadlines:
- February 20, 2026: A Press Information Bureau release quoted project adviser Mohinder Singh as saying the line was targeted for December 2027 and that about 90% of the project work was complete.
- March 2026: When tunnel No. 8 (4.148 km) broke through, NFR said digging was now complete in 13 of the line's 14 tunnels. It described "highly weak, weathered and fractured rock strata" and the difficulty of working beside the NH-10 corridor, The Indian Express reported. Commissioning was still put at December 2027.
- August 25, 2026: MP Subba asked NFR's zonal users' committee in Guwahati to speed up the project. India Today NE reported the deadline as December 2027.
- October 2026: The Times of India reported about 75% physical progress and an "end of 2027" target.
- November 18, 2026: NFR gives June 2028.
The two progress figures are not like for like: 90% was a site adviser's estimate of "project work", 75% is reported physical progress.
Reported costs also differ. The Indian Express, citing the Railway Minister's Lok Sabha answer of March 11, 2026, gave the latest estimated cost as Rs 11,973 crore, with Rs 8,358 crore spent up to March 2025 and Rs 2,940 crore set aside for 2025-26. The Times of India put the cost at Rs 17,124 crore in October.
The same answer pointed to one known hold-up: forest land diversion proposals for Riyang Yard (3.26 hectares) and Melli Yard/Bridge-9 (3.12 hectares) pending with the West Bengal government since March 2024. Of the line's length, 41.55 km lies in West Bengal and only 3.41 km in Sikkim, so most clearances sit outside Sikkim.
What the line looks like
About 86% of the route, 38.62 km, runs through 14 tunnels. The longest tunnel is about 5.3 km. There are 13 major and 10 minor bridges. Five stations are planned at Sivok, Riyang, Melli, Rangpo and an underground halt at Teesta Bazar. The railhead will be at Rangpo, on the Sikkim-West Bengal border, about 40 km by road from Gangtok.
What this means for Sikkim
Sikkim is the only North Eastern state with no railway at all. When NFR said this week that every operational broad-gauge line in the region was electrified, Sikkim was missing from the state-wise table, as NEInsider reported.
For now, almost all people and goods reach the state by road along the Teesta valley. The railways say the line will keep essential supplies steady; for traders in Rangpo, Singtam and Gangtok, a border railhead would mean a second route for goods. Under the new target, the line would open just as the 2028 monsoon, the season of landslides on that road, begins.
How it compares
Nagaland's Dimapur-Kohima line is 50% complete with a December 2029 target, almost 23 years after it was sanctioned, NEInsider reported last week. Mizoram's Bairabi-Sairang line now runs to Sairang, near Aizawl; the Times of India counts four NE capitals with rail links. Sivok-Rangpo would stop at Rangpo, not Gangtok, so Sikkim would still need a further line to bring trains to its capital.
What happens next
- Coordination framework: NFR and the state are to set up a joint mechanism; no date announced.
- Gangtok extension: The Times of India reported in October that the PM GatiShakti Network Planning Group had taken up a proposed 34-km Rangpo-Gangtok line, estimated at about Rs 9,000 crore.
- Melli-Dentam: Subba has sought early completion of the final location survey and project report.
NEInsider will update this story if NFR explains the new date or publishes current progress figures.
Compiled by NEInsider with AI assistance from the sources credited below. How we use AI
Sources and credits. With inputs from The Morung Express (18 Nov) https://www.morungexpress.com/nfr-reviews-sivok-rangpo-railway-project-with-sikkim-cm ; IANS via The Hawk (18 Nov) https://www.thehawk.in/news/states-and-uts/sikkim/sikkim-to-get-first-ever-rail-connectivity-by-june-2028-as-work-on-strategic-sivokrangpo-project-progresses ; background: PIB (20 Feb 2026) https://www.pib.gov.in/PressReleasePage.aspx?PRID=2231092 ; The Indian Express (19 Mar 2026) https://indianexpress.com/article/india/train-to-sikkim-sevoke-rangpo-railway-project-tunnel-breakthrough-commissioning-2027-10590537/ ; India Today NE (25 Aug 2026) https://www.indiatodayne.in/sikkim/story/sikkim-mp-pushes-for-faster-rail-connectivity-urges-early-completion-of-sevoke-rangpo-line-1442733-2026-08-25 ; The Times of India (6 Oct 2026) https://timesofindia.indiatimes.com/business/india-business/sikkim-to-get-train-connectivity-for-first-time-as-44-5-km-sivok-rangpo-project-reaches-75-progress-to-be-completed-by-december-2027-railways-fast-tracks-rs-9000-crore-gangtok-rail-link-as-well/articleshow/134725767.cms